pace development
  • Home
  • Properties
    • Nimit Langsuan
    • MahaSamutr
      • MahaSamutr Country Club
      • MahaSamutr Villas
    • MahaNakhon
      • The Ritz-Carlton Residences, Bangkok
    • Saladaeng Residences
    • Ficus Lane
  • Retail
    • DEAN & DELUCA
  • Company Profile
    • Vision and Mission
    • Background
    • Corporate
    • Management Team
    • Corporate Social Responsibility
  • investor relations
  • News
    • Press Release
    • PACE E-Newsletter
    • Momentum
  • Contact
  • Career
  • TH
  • EN
MahaNakhon Construction: Piling Complete
MahaNakhon Construction: Piling Complete





Back

MahaNakhon Construction: Piling Complete


Piling work for Bangkok’s tallest building was completed 100% in February, for both the main tower and the smaller “CUBE” retail building. The next step of work has been excavation to a depth of approximately 18m below ground level, this underground area forms the 4 below ground car park levels and plant room for the retail complex. In March, below ground works have continued on site, including commencing basement construction and concrete core which is progressing on schedule. As of early April, work on the lowest basement level B4 was already completed with work underway on B3. All below ground works for the basement levels are scheduled to be completed by the end of May 2012 after which above ground work for CUBE will commence and the next phase of the Main Tower will be started in July. The CUBE retail building target completion date is 3rd quarter 2013.

© 2024 PACE Development Corporation PLC. 152 Kian Gwan Building 3,4th Floor
Wireless Road, Lumpini, Pathumwan, Bangkok 10330 Thailand. All Rights Reserved