MahaNakhon Construction Continues
Over the last 6 months, 2 important milestones have been
achieved. The CUBE is now topped off, with façade work now
completed and tenants are already moving in to fit out their new
premises in Bangkok’s newest lifestyle shopping center.
MahaNakhon Tower below ground work is now completed, and
with the basement and piling providing the foundation for the
314m tower finished, work above ground has now commenced.
It is expected that the building will rise at the rate of around 2
floors per month, speeding up over time.
As always, the devil is in the details, and the last 6 months have
also included selecting the media wall system, which at 1,000
sq.m. will the country’s largest single outdoor screen, showing a
variety of content generated specifically for MahaNakhon.